Free PMI-ACP ExamPosted On 21/08/2025|0 Comments Welcome to your Free PMI-ACP Exam An Agile team is working on a SCM project with a total of 600 story point to deliver. At the end of the 3rd iteration, the team had successfully delivered 81 story points. The team was able to successfully address some improvement opportunities and during the 4th iteration the team was able to deliver 39 story points. Assuming that the team maintains its current velocity and no more story points are added to the project, which of the following statements is correct? A. The velocity has decreased, which implies that the team would require another 16 iterations to complete the project. B. The velocity has increased, which implies that the team would require another 16 iterations to complete the project. C. The velocity has decreased, which implies that the team would require another 18 iterations to complete the project. D. The velocity has increased, which implies that the team would require another 18 iterations to complete the project. None English Female English Male The linear trend of a burndown chart is usually: A. Downward sloping B. Upward sloping C. Horizontal to the y-axis D. Vertical to the y-axis None English Female English Male An Agile team collected all the requirements for a particular project iteration. These requirements were translated to the design specifications followed by the development work. During the acceptance testing, the team realized that some of the design assumptions were not valid and most of the features requires rework. What went wrong? A. The team fell into the trap of mini-waterfall. B. The team didn’t document the assumptions in the design specifications. C. Nothing went wrong, Agile teams welcome rework. D. The requirements collection process was probably flawed. None English Female English Male Time's up